Chilton Saltlands Penstocks – Project Update

November 27, 2023

Chilton Saltlands Penstocks – Project Update

Hanevo are pleased to report that works have been completed on Phase 1 of the ‘Chilton Saltlands Penstocks Upgrade’ project. This phase of works comprised Mechanical & Electrical works to repair the Inlet Penstocks and make provision for future actuation. Working in close collaboration with Wessex Water, completion of these works was achieved whilst over-pumping flows of 200l/s back into the rising main to facilitate access into the 26ft deep penstock sumps. Noteworthy is that over-pumping was only permitted during daytime working hours and coupled with the weather conditions, this made for a challenging phase of the project. 

 

The successful completion was helped by careful pre-construction planning and the dedication of the on-site delivery teams. As this site is contained within a built-up housing area, special attention to mitigation measures for noise and security concerns formed a key element within our CDM setup. Phase 2 of the works entails the installation and automation of Rotork Actuators and their subsequent commissioning. These Phase 2 works are scheduled for early January 2024.

 

Richard Gray, Senior Electrical Project Engineer at Hanevo noted “These important Phase 1 works were not without their challenges. The intricacy, depth, location, and over pumping requirements of the works meant that close collaboration with our client was paramount. Safety was the key driver in planning. This attention to detail combined with the skill of the Hanevo installation teams is a source of pride to all involved particularly when the client PM wrote to Hanevo stating “a fantastic amount of work has been completed by Paul and the team on a difficult job”


December 17, 2024
HANEVO Proud Sponsors of the GESH Care Awards 2024
October 1, 2024
Hanevo are delighted to have been awarded the Westwood WRC screening works electrical package, with the works to commence in mid-October.
September 16, 2024
HANEVO have been awarded a critical project to replace the roof coverings to the D Block at St Helier Hospital.
September 16, 2024
 HANEVO well underway on Therapy Gardens for Epsom Hospital Patients
August 9, 2024
HANEVO have been awarded the fit out, from shell and core, of a new privately run Eye Clinic in London. Commenced on site in June 2024, and being completed by November, the new facility will provide high quality ophthalmic clinic for use by the local community, giving greater choice to patients and complement the existing healthcare provision in the local area.
August 9, 2024
Works are progressing on programme at Hanevo’s ‘Vale Road’ project - ‘Sludge Screening M&E Works’.
August 9, 2024
Hanevo has completed all civils and mechanical works at North Nibley – which is the first of two awarded EDM Advanced Contracts – the other being Wootton Bassett STW which commences Monday 12th August.
August 9, 2024
Works are nearing completion on site at our ‘Shepton Mallett Blowers’ project. The project comprises Mechanical, Electrical and Commissioning works, to install 5 new blowers and associated stainlesss steel pipework, valves and fittings.
July 24, 2024
The Hanevo team is delighted to confirm our passing of the SafeContractor audit.
February 29, 2024
HANEVO have been awarded the full internal and external refurbishment of the Grade II Listed Heywood House Building for ACS International School in Cobham, Surrey.
More Posts