An Uplifting Saturday for HANEVO at Frimley Park Hospital

March 25, 2026

An uplifting Saturday for HANEVO at Frimley Park Hospital

HANEVO have successfully completed a major milestone on our project from Frimley Health NHS Foundation Trust, with the installation of the new Air Handling Unit on the roof adjacent to the Theatre 7 being upgraded.

The installation of the new AHU was a significant challenge requiring extensive co-ordination and planning with many stakeholders.  Owing to site constraints, with a landlocked site at the centre of the live hospital estate, and significant unit weights being installed, several lifting solutions were investigated, including serious consideration of a helicopter lift.  Working closely with our specialist crane providers, we developed a solution involving a 300t mobile crane with fly-jib attachment, lifting units weighing over 1.5t at a 77m radius over the live hospital estate.


Planning and co-ordination work by HANEVO and the Trust required clearance of the waste compound yard, planning of bin movements, traffic management around road closures on the estate, as well as co-ordination with the air ambulance helicopter service on the site.



In planning the works, we worked closely with the AHU suppliers to optimise the section sizes to suit available crane capacity, including removal of cooling coils and fans to be lifted separately to bring weights down to an acceptable limit.


To minimise disruption and impact, the crane lift was carried out over a full Saturday.  The 300t crane required a smaller mobile crane to install the fly jib and complete rigging, a 3 hour operation, with a strategically timed delivery of the sectional AHU in its enclosure to minimise road closure time and impact on traffic flow.  The AHU was lifted in 3 main component sections, with 7 additional lifts of smaller plant and ductwork undertaken.


Commenting on the project, Pre-Construction Director Jozef Mountain stated “this complex lifting operation was months in the planning, and it was incredible to see the scale of the operation in full flow on site.  We cannot understate the significant input of all parties, from our client at Frimley Health NHS Foundation Trust and their many stakeholders, through to out equipment and plant providers, in ensuring that this challenging and critical stage of the project was completed successfully and safely.  This is a true example of successful collaboration across a full project team”.


March 30, 2026
HANEVO complete heavy lifting of new chillers at St Helier
February 25, 2026
Shepton STW Chemical Storage Tank Wessex Win for Hanevo
February 24, 2026
St. Georges Hospital washroom project reaches mid-way point for HANEVO
February 23, 2026
HANEVO approaching the latter stages of the MAU & Maternity Development at Epsom General Hospital
February 23, 2026
UCLH Appoint HANEVO to deliver LED lighting efficiency programme of works
February 22, 2026
Two New Emergency Lighting projects awarded to HANEVO at Epsom & St Helier
February 21, 2026
Award of Saltford STW Chemical Storage Tanks
February 20, 2026
Theatre 7 Refurbishment at Frimley Park Hospital
October 9, 2025
HANEVO awarded place on Wessex Water AMP8 ‘Design & Build Contractors (Minor Works)’ Framework.
September 19, 2025
Hanevo Support St Joseph’s Foundation Golf Classic