Swanage UV Progress

February 20, 2024

Swanage UV Progress

Works are underway on Phase 2 of the ‘Swanage UV Installation’ project. The project involves the installation a duty/standby UV System, Pumps, Mixers and Copa-sacs with accompanying instrumentation and control systems along with a new flooring system over the UV Sump.


Phase 1 involved the installation of 100 Metres of 200mm diameter Stainless Steel pipework in the long void area behind the cliff face.


Phase 2 involves the remaining pipework installation, along with further mechanical and electrical works, which will be completed and commissioned in February 2024. 


Prior to contract commencement, the client had envisaged that part of the site would be shut down to facilitate the works. However, this could not be facilitated, and the Hanevo team, working with the client, re-evaluated and amended the methodology in devising a temporary works solution that maintained site operations.


December 17, 2024
HANEVO Proud Sponsors of the GESH Care Awards 2024
October 1, 2024
Hanevo are delighted to have been awarded the Westwood WRC screening works electrical package, with the works to commence in mid-October.
September 16, 2024
HANEVO have been awarded a critical project to replace the roof coverings to the D Block at St Helier Hospital.
September 16, 2024
 HANEVO well underway on Therapy Gardens for Epsom Hospital Patients
August 9, 2024
HANEVO have been awarded the fit out, from shell and core, of a new privately run Eye Clinic in London. Commenced on site in June 2024, and being completed by November, the new facility will provide high quality ophthalmic clinic for use by the local community, giving greater choice to patients and complement the existing healthcare provision in the local area.
August 9, 2024
Works are progressing on programme at Hanevo’s ‘Vale Road’ project - ‘Sludge Screening M&E Works’.
August 9, 2024
Hanevo has completed all civils and mechanical works at North Nibley – which is the first of two awarded EDM Advanced Contracts – the other being Wootton Bassett STW which commences Monday 12th August.
August 9, 2024
Works are nearing completion on site at our ‘Shepton Mallett Blowers’ project. The project comprises Mechanical, Electrical and Commissioning works, to install 5 new blowers and associated stainlesss steel pipework, valves and fittings.
July 24, 2024
The Hanevo team is delighted to confirm our passing of the SafeContractor audit.
February 29, 2024
HANEVO have been awarded the full internal and external refurbishment of the Grade II Listed Heywood House Building for ACS International School in Cobham, Surrey.
More Posts