Swanage UV Progress

February 20, 2024

Swanage UV Progress

Works are underway on Phase 2 of the ‘Swanage UV Installation’ project. The project involves the installation a duty/standby UV System, Pumps, Mixers and Copa-sacs with accompanying instrumentation and control systems along with a new flooring system over the UV Sump.


Phase 1 involved the installation of 100 Metres of 200mm diameter Stainless Steel pipework in the long void area behind the cliff face.


Phase 2 involves the remaining pipework installation, along with further mechanical and electrical works, which will be completed and commissioned in February 2024. 


Prior to contract commencement, the client had envisaged that part of the site would be shut down to facilitate the works. However, this could not be facilitated, and the Hanevo team, working with the client, re-evaluated and amended the methodology in devising a temporary works solution that maintained site operations.


June 13, 2025
HANEVO Awarded New Stable Building and Facilities for Equine Therapy Hub
June 9, 2025
HANEVO awarded place on Wessex Water ‘M&E Contractors (Minor Works)’ Framework.
June 6, 2025
SEON Vision - Hanevo Build State of the Art Eye Clinic now providing treatment to patients in the Kingston community.
June 4, 2025
SMART Obstetrics Theatres for Epsom Hospital
December 17, 2024
HANEVO Proud Sponsors of the GESH Care Awards 2024
October 1, 2024
Hanevo are delighted to have been awarded the Westwood WRC screening works electrical package, with the works to commence in mid-October.
September 16, 2024
HANEVO have been awarded a critical project to replace the roof coverings to the D Block at St Helier Hospital.
September 16, 2024
 HANEVO well underway on Therapy Gardens for Epsom Hospital Patients
August 9, 2024
HANEVO have been awarded the fit out, from shell and core, of a new privately run Eye Clinic in London. Commenced on site in June 2024, and being completed by November, the new facility will provide high quality ophthalmic clinic for use by the local community, giving greater choice to patients and complement the existing healthcare provision in the local area.
August 9, 2024
Works are progressing on programme at Hanevo’s ‘Vale Road’ project - ‘Sludge Screening M&E Works’.
More Posts