Frome Success

July 19, 2022

FROME SUCCESS

Hanevo has reached completion stage of the ‘Frome STW Recirculation Building Upgrade’ contract for Wessex Water.

Wessex Water handed over control of the Recirculation building to Hanevo in May 2022, under which a full CDM site setup was established.


The project involved all civil, mechanical, electrical & ICA works, which included the removal of existing shaft driven pumps, pipework, control panel and installation of new, whilst keeping the site operational. New instrumentation was installed to facilitate control of the pumps and new flooring to aid removal of the new pumps. As part of the project, the existing Mains Cable to the building required replacement. This involved the installation of 9 new cable pits and cabling along a 220M route up to the Inlet MCC Building.

 

The main project objective was to increase recirculation pump efficiency and flow rates. The anticipated improvements have been surpassed with the installation of the new pumps, lending itself to positive commentary from Wessex Operations and Process Staff. Wessex Water Project Manager for the scheme, while thanking Hanevo noted, “The project has been delivered both on time and within our budget constraints”.

 


December 17, 2024
HANEVO Proud Sponsors of the GESH Care Awards 2024
October 1, 2024
Hanevo are delighted to have been awarded the Westwood WRC screening works electrical package, with the works to commence in mid-October.
September 16, 2024
HANEVO have been awarded a critical project to replace the roof coverings to the D Block at St Helier Hospital.
September 16, 2024
 HANEVO well underway on Therapy Gardens for Epsom Hospital Patients
August 9, 2024
HANEVO have been awarded the fit out, from shell and core, of a new privately run Eye Clinic in London. Commenced on site in June 2024, and being completed by November, the new facility will provide high quality ophthalmic clinic for use by the local community, giving greater choice to patients and complement the existing healthcare provision in the local area.
August 9, 2024
Works are progressing on programme at Hanevo’s ‘Vale Road’ project - ‘Sludge Screening M&E Works’.
August 9, 2024
Hanevo has completed all civils and mechanical works at North Nibley – which is the first of two awarded EDM Advanced Contracts – the other being Wootton Bassett STW which commences Monday 12th August.
August 9, 2024
Works are nearing completion on site at our ‘Shepton Mallett Blowers’ project. The project comprises Mechanical, Electrical and Commissioning works, to install 5 new blowers and associated stainlesss steel pipework, valves and fittings.
July 24, 2024
The Hanevo team is delighted to confirm our passing of the SafeContractor audit.
February 29, 2024
HANEVO have been awarded the full internal and external refurbishment of the Grade II Listed Heywood House Building for ACS International School in Cobham, Surrey.
More Posts