Galliford try

 Galliford Try - Southern Water


Electrical & Domestic Water Backlog

As part of Southern Water’s ongoing environmental legislation obligations, main contractor Galliford Try were contracted to undertake asset upgrades to 22 sites across the South East operating region. Hanevo were sub-contracted to Principal Contractor Galliford Try on these notifiable projects to investigate & implement necessary improvements to flows & spills monitoring (Flows 3&4) to pump stations & sewage treatment works with civil engineering, mechanical & electrical works undertaken in house or with specialist supply chain partners.

Our first requirement was to survey, investigate, design and implement upgrades to the existing facility to ensure
accurate monitoring, back to the central
Southern Water system, of flows into and
from the site in storm conditions.

All works were required to be designed so that installation could be done whilst the existing facility remained fully operational.

Our solution involved the introduction of a new storm overflow chamber which housed the new MAG meter to monitor flows. This would then be used to monitor diverted flows from either the existing wet well or storm tank outlet, with the current outflow removed or temporarily bypassed from service.

To enable this to be installed concurrently with ongoing site operations, the new
chamber was installed on an agreed location on the site, with new below ground pipework to allow full and final diversion once works were complete.

As sub-contractor to Galliford Try, we were required to work in full accordance with their overarching CPH&S Plan. Our RAMS were developed collaboratively to ensure full alignment to expectations on site. We were involved in pre-start design & risk workshops, providing buildability advice to the design team & Principal Designer. We supervised all works under our control, co-ordinating with the wider workforce of the Principal Contractor. This included on-site management of supply chain partners for specialist elements (i.e. MCERTS/Emersons) reviewing process & incorporating into RAMS.

Some the new chamber being constructed, were on public land, we also supported the Client, Southern Water, and Principal Contractor in their discussions with land owners.


We worked with the Principal Contractor in supporting any EW or CE processes under the contract & at completion provided all necessary information for our works to the Principal Designer to support the H&S file & HAZOP review with Southern Water

The Works undertaken:


  • Detailed ground investigation surveys to inform design solution & temporary works.
  • Sheet piled coffer dam for temporary works to new chambers, designed wit supply chain partners. Trench box solution used for pipe excavations Monitored during install & use by in-house temporary works engineers.
  • Continual pumping of groundwater when required, with pump sizing designed in house. Over pumping operations during both change overs and for over pumping storm water direct to outfalls to maintain site compliance. 24/7 manned auto control over pumping when pumping to outfalls.
  • Excavate, install, test & backfill PN16 ductile iron pipework of varying diameters to various  depths of up to 4m, under gravity from existing wet well or storm tank to new chamber & on to outfall.
  • New pipework connections in existing wet wells, core drilled at low flow within temporary works structure.
  • Proprietary edge protection & access.
  • Excavate & install new ducting and/or above  ground containment for controls / telemetry cabling. Supply and installation of cabling from mag flow meter controller to Milltronics unit and onto the site telemetry outstations.
  • New chamber covers & reinstatement of soft & hard landscaping.
  • Issuing of MCERTS/SP ICA Forms to Employer with detailed O & M manuals



Sustainability

Our Values


Latest News

29 Feb, 2024
HANEVO have been awarded the full internal and external refurbishment of the Grade II Listed Heywood House Building for ACS International School in Cobham, Surrey.
23 Feb, 2024
Hanevo are in the planning and procurement stage on the recently awarded project ‘Bridport Blowers’.
21 Feb, 2024
Works are nearing completion on the ‘Dosing Tanks Replacement’ projects at Westbury and Thingley.
Show More
Share by: