D Block Goods Lift Replacement - St Helier Hospital

Completed in December 2025, Hanevo delivered the replacement of the D Block goods lift at St Helier Hospital to restore critical access to basement plant and storage areas.


The project involved extensive structural alterations to the existing lift shaft to accommodate a new 1000kg chain-driven electric goods lift with additional landing levels.



The works were coordinated around ongoing hospital operations in adjacent and occupied areas.


Works included:


  • Installation of protective hoardings and full-height shaft scaffold
  • Strip-out of existing lift equipment and shaft preparation works
  • Structural alterations and formation of new landing openings
  • Waterproofing and fire protection works within the lift shaft
  • Installation of new 1000kg chain-driven electric lift and landing gates
  • Electrical upgrades, shaft lighting installations and LOLER certification