Vale Road Yeovil - Sludge Screening M&E Works
Hanevo completed the ‘Vale Road Sludge Screening M&E Works’ project in 2024, totalling £536k.
For this project, Hanevo acquired the handover of PC Role / CDM Management from Bartletts Civils in Mid May 2024 and works were ongoing until September, with Commissioning completing in October.
The driver for this project is to ensure that the S Max is safe by reducing H2S Concentrations. Alternative screening provisions for imported sludge were required to remove any rags from the thickened sludge transferred from Yeovil to Ham thus maximising reactor operational capacity.
Hanevo’s scope involved Fabrication, Mechanical, Electrical works - to install a new MCC & Kiosk, Access platform and Staircase, Strainpress Chutes, Break Tank, Various new pumps, pipework, valves and accessories with associated instrumentation.
Jamie Tate, Electrical & Commissioning Engineer at Hanevo noted: “The whole Wessex Water team were incredibly hospitable in allowing us to setup our CDM site for the project duration, The projects has been a great success”.