Bellrock PLC. 
Coventry Health Care, Clay Lane

Turnkey delivery of significant refurbishment at Coventry Health Centre. Included development of an 8,500 sq. ft. space on the 1st floor of a live Health Centre, converting GP and Dental Practice into a new Satellite Renal Dialysis Treatment Centre.

Strict programming requirements because of commitments to prearranged critical appointments for dialysis treatment in the new centre. The Health Centre was kept live throughout the works while undertaking works directly above the main entrance, health centres, surgeries etc. 

Works involved: Full soft strip of furnishings and equipment; Builders work remodelling through structural works; Install of specialist RO plant; Full M&E install and integration into existing systems; backup generators during the works; fire protection works; toilet core fit out; new ceilings, partitions and floor finishes; Carpentry, decoration and FFE.

Whittington Health NHS Trust  
Backlog Maintenance

Completed in 2018, this scheme was made up of 3 main phases of works, all undertaken in a live hospital environment which demanded maximum sensitivity to the patients and the ongoing care they required, as well as facilitating staff.

Electrical upgrades to the aging main hospital blocks: Condition Reporting, Fault finding and rectification; Replacement of non compliant distribution boards with minimal and strictly managed downtime; Full testing and certification in accordance with BS7671; Updating of Trust asset information. •

Domestic Water upgrades: New and future proofed HW pipework to critical NICU department; Bypass pipework to hazardous domestic water tanks; Cleaning and upgrading main external hospital feed tank ; Dead leg removal through out hospital buildings to achieve compliance regulation.

Control and performance upgrade to Mortuary AHU to meet user need and comply with specification.

Whittington Health NHS Trust 
Fire Remediation

Following success of the backlog maintenance scheme (see above), awarded this project to upgrade fire protection to the ageing hospital.

Due for completion in June 2020, works are carefully programmed around live ward access to ensure full hospital operation as usual and the comfort of patients. Much of the works are out of hours and planned around clinical care needs. Project is divided into 4 main parts:

Fire Doors: replacement of 190 fire door sets and the maintaining of 50 more to bring up to specification, using FDIS accredited installers.

Fire Stopping: detailed surveys and rectification of all fire zone partition lines, with wall & floor penetrations filled. Fire Alarms: Working with the trust specialist to upgrade the detection and alarm system to all areas.

Emergency lighting: installation of 500 new fittings to meet regulations.

Heathrow MBBR
Replacement of Mechanical Equipment

Assembly and installation of over 1600no. free issue stainless steel aeration diffuser heads in 2 recently installed 15m diameter glass fused steel MBBR aeration tank.

Installation of all associated PVC pipework between diffusers and stainless steel pipework to connect to the aeration blowers.

Fabrication and installation of stainless steel double pipe support brackets for the horizontal headers which run above one another.

Leak and pattern testing on the installed grids for each tank in accordance with the Sanitaire process.

Access to works was via an 800mm hatchway in the side of the tank and, although having an open top, full confined space processes were followed.

South East Water (various sites)
Live Process Plants

Full compliance planning and process risk assessments undertaken alongside client team and principal contractor, operators and process scientists, to develop and implement a detailed compliance plan covering all process risks.

Extensive sequential phased works to enable our installation, test and commission of a full new Profibus system.

Daily meetings to discuss process need, and micro programming for shut downs and isolations in accordance with strict permit procedures.

Assistance with the Installation of temporary borehole headwork pumps to maintain extraction during works.

Extensive temporary generator installations to enable full MCC shut downs, removals and replacement with no operational impact.

London Project   
Pipe Installation

A recent project with an example of utility diversion work.

Our team has a vast combined experience of over 50 years in civil engineering, utilities diversion and MEICA while our project team is made of individuals with the right experience, competence, attitude and drive to deliver maximum performance through all stages of the project.